River bank He needed to modernize and expand his home. In August 2020, amid the coronavirus pandemic, the leadership took an important decision, as it found the right scenario to launch a project, which for 6 years was around the heads of the members of the board of directors and which was always run by Marcelo Gallardo Was: Completely renovate the memorial’s playing field. then driving Advanced with another ambitious objective: to expand the potential of Antonio Vespuccio Liberty.

this thursday was invited to visit infobae to commemorate To see how work is progressing on the lower ring of the stadium (where the athletics track was located). The Nunez organization is confident that it will have three of the four new stands available by the beginning of 2023. Centenario Media also awaits the opening of 30 boxes and a 700-square-metre restaurant. Growth in remodeling is at “40%”, as highlighted by President Jorge Brito,

There are three details that stand out in the works. The new brand manual incorporates gray in various shades as a complementary color to white, red and black which represents River Plate., In this way, it follows the trend of other great stages, such as Tottenham or the Santiago Bernabeu.

Beyond the fact that gray seeks to convey modernity and spaciousness, it also represents savings in the medium and long term. is that Red, according to studies conducted by the company in charge of the work, turns pink in just five years. Grey, on the other hand, lasts (about three times) longer.

At this point, Jorge Brito elaborated: “We are aware and we listen to the fans, but there are technical issues. The new stadiums go darker for durability and gray also has a connection with the river. Red is about five.” Turns pink over a period of years, while white is not recommended as it is not a covered stadium.

Another important detail: The single entrance tunnel from the complexes to the playground shall be located between two substitute benches. And the giant screen will go head to head. However, the design includes two extra-wide panoramic screens,

The President also emphasized the importance of returning the lessons to Antonio Vespuccio Liberti to finance this work: “We have more than $6 million in income for the 14 lessons that also contribute to the funding of the work.”

It is worth remembering that in the first months of the pandemic, leaders took advantage of the fact that public appearances were not allowed in stadiums at that time, paving the way for the refurbishment of the playing field. The Irish company Sis Gras was contracted to improved drainage and switched to a hybrid lawn (After lowering the ground level by about two meters, 5 percent artificial and 95 percent natural grass was planted). In the underground modifications that are now near the monument, it is evident that the pipes were replaced for PVC ones, a phase of pipe laying in the rainwater gutter was done, later to the geotextile mantle and waterproofing layer. After excavating compacted soil bases for installation of pluvial drainage and aeration pipes, they were covered with gravel to improve runoff. A layer of sand and air conditioning systems (heating and cooling) were also laid.

In addition, the monument’s bathrooms were remodeled, new gastronomic stalls were built in the lower grandstands, WIFI 6 was installed (key to later turning it into a smart stadium), fences were removed in the upper centenario to improve visibility. and there were improvements in the area for wheelchair users.

Then, in late March, work began on the expansion of the monument, which This would make it the largest-capacity football club-related stadium in South America, with a capacity of 81,000 spectators.

Most of the money from the works came through naming. of monumental (The GDN Group, which has Francisco de Narvez as its main head and has Changomas and Punto Mayorista under its class, among other companies, Will invest about $20 million for 7 years). The second part will come from the organization’s actual resources, such as pre-sales of tickets for these boxes and stalls that will be built in the short term and in play.

This part of the reforms will be divided into two parts, and the first focuses on building three of the four lower stands (They will be in the area where the ad banners are currently located): Sivori, Centennial and San Martin. Belgrano, on the other hand, will be held in the next stage, as the River Plate institution must be relocated first (this may be within the club or on nearby property). It is scheduled to be completed in February 2023 and will cost approximately $20 million.

Any old claim of members and supporters will also be fulfilled, such as change of seats. First, the advance would be made with those located in the lower and middle stands. In addition, two tunnels leading from the locker room will be built, allowing both teams to exit the center of the pitch simultaneously, as is the case in most European stadiums.

In Central Centenario, 30 new boxes will also be built, a 700 square meter restaurant with views of the Barrio River and the river. to commemorate With independent access, and a new garage floor (for 227 vehicles and for pedestrian access to the stadium on the ground floor). In addition, San Martin will feature new restrooms and a kitchen with new single tunnel views, a new referee’s locker room and anti-doping controls, replaced audio systems and a new medical department. Ground floor of Centenario Grandstand.

Another important change would be the distribution of masses, because 71% will be stalls and the remaining 29% will be popular. The current lower portion, as well as the lower portion to be built, will be popular, both behind the Sivori Grandstand and the arches of the Centenario. This will be followed by a full ring of stalls at the bottom, San Martin and Belgrano stalls, and the middle stalls. In the case of Centenario and Sivori, these stalls would have nothing to do with the popular ones.

Phase II, which will also cost around $20 million, is to be completed in July 2024. The bottom ring will close. With the work in Belgrano, 46 ​​boxes would be added to Media Sivori and thus the stadium would cease to operate. Two more parking floors will also be added (402 new garages, completing five parking levels and a new pedestrian bridge on the upper level, with connections at box level). In this way, it will be able to take 1141 cars home.

This is the gallery where the work is most advanced.

– Opening of the new Marathon Gate for vehicular entry (in the area adjacent to the Belgrano stalls).

A construction fence was installed for the manufacture of new boxes.

The bathroom, grandstand bar and medical post were demolished.

-30 new boxes will be built and a 24/7 restaurant of 500 m (interior) + 215 m2 exterior, with new circulation and cladding, with views of the river neighborhood and sports field. – Foundations for the lift tower completed Went.

-One third finished concreting (Tier stage).

The single exit tunnel to the playing field is 70% complete (excavation and concreting). The support framework for the same is being implemented.

Seats will start coming soon.

– Foundation stage finished (the base that will support the entire weight of the structure).

-Currently the concrete work of the new frame is being done.

– The foundation phase is underway.

– New lower lower grandstands in the Sevori, San Martín and Centenario sectors.

– Replacement of seats: removal of existing seats in the lower, upper, middle and hospitality stands of San Martin, waterproofing, new circulation and placement of new first class retractable seats, quality in accordance with FIFA standards; Belgrano low top, middle, and hospitality boxes; Media centenarians and boxes. A total of 17,157 new seats will be completed for this phase.

-There will be new desks in the Belgrano Grandstand (247 seats) in the center of the press sector.

-30 boxes in Centenario Media and a 700 square meter restaurant with views of the neighborhood and playground of the river, with new circulation and coverings.

-New circulation and covering in boxes at the Belgrano Grandstand.

-New garages: new parking level and pedestrian access to the stadium on the ground floor. 227 garages will be added.

– Enlargement of the paddock San Martin, as it will go from 200 to 500 square meters.

– Expansion of the gastronomic sector in San Martín Media

-New audio system in the stadium.

-New Medical Department on the ground floor of Centenario Grandstand.

– replacement and waterproofing of the seats in the lower Belgrano lower stand; Sivori Media & Box; San Martin, Belgrano, Centenario and Sivori High. A total of 40,565 seats will be replaced, making the entire stadium complete.

Construction of 46 boxes at Sivori Grandstand.

-Execution of two more parking levels. This way, with connections at the box level, there will be 402 new garages, completing five parking levels and a new pedestrian bridge on the upper level. Its final capacity will be 1,141 cars.

-New mixed area on the ground floor of the Belgrano Grandstand.

Save my name, email, and website in this browser for the next time I comment.

Nation World News is the fastest emerging news website covering all the latest news, world’s top stories, science news entertainment sports cricket’s latest discoveries, new technology gadgets, politics news, and more.

Contact us: contact@nationworldnews.com

© Copyright 2021 Nation World News All Right Reserved.